Explore · Housing and development

How long does a permit take?

Surrey's reported processing times against its own targets, and what the clock actually measures.

For homeowners, builders and anyone opening a business. A processing time is a City measure of its own review. It is not the whole wait from first idea to a finished project.

Surrey's figures were last updated by the City on November 16, 2026. Checked November 18, 2026.

Surrey, current processing times

Reported times against targets

The bar is the current average. The gold line is the City's target. "Home" here means a new single family house or duplex, as the City defines it.

Building permits

  • New home (single family or duplex)4 weeks now · target 10 weeks

    Within target. 4 weeks on average, against a target of 10 weeks.

  • Addition or renovation, home (single family or duplex)2.4 weeks now · target 6 weeks

    Within target. 2.4 weeks on average, against a target of 6 weeks.

  • New tenant improvement3.4 weeks now · target 10 weeks

    Within target. 3.4 weeks on average, against a target of 10 weeks.

  • Minor tenant improvement1 day now · target 3 business days

    Within target. 1 day on average, against a target of 3 business days.

  • Medical clinic tenant improvement2.1 weeks now · target 3 weeks

    Within target. 2.1 weeks on average, against a target of 3 weeks.

Rezonings

  • Rezoning, home (single family or duplex)15 weeks now · target 12 weeks

    Slower than target. 15 weeks on average, against a target of 12 weeks.

  • Rezoning, multi-family, commercial and industrial9.2 weeks now · target 16 weeks

    Within target. 9.2 weeks on average, against a target of 16 weeks (add 4 weeks if the Advisory Design Panel reviews it).

Averages of permits processed in the last 30 days for building permits, and the last 6 months for rezoning. Extended City closures, such as the December break and Council breaks for rezoning, are accounted for. Source: City of Surrey, Permitting Timelines, last updated November 16, 2026.

The figures as a table
Surrey processing times, last updated November 16, 2026
Permit typeCurrentTargetWhen the clock starts
New home (single family or duplex)4 weeks10 weeksAfter referrals and a complete site servicing review
Addition or renovation, home (single family or duplex)2.4 weeks6 weeksThe City does not say
New tenant improvement3.4 weeks10 weeksAfter a complete and accurate building permit application is submitted
Minor tenant improvement1 day3 business daysAfter a complete and accurate building permit application is submitted
Medical clinic tenant improvement2.1 weeks3 weeksAfter a complete and accurate building permit application is submitted
Rezoning, home (single family or duplex)15 weeks12 weeksAfter the initial review and resolution of all major deficiencies
Rezoning, multi-family, commercial and industrial9.2 weeks16 weeks (add 4 weeks if the Advisory Design Panel reviews it)After the initial review and resolution of all major deficiencies

The clock

When does the measurement start?

Not when you hit submit. Surrey's own answer to "Does the timeline start when I submit my application?" is no. Some of the wait happens before the clock starts.

  1. 1 · You apply

    The application arrives. The clock is not running yet.

  2. 2 · Before the clock

    Referrals, servicing review or fixing major gaps, depending on the permit type.

  3. 3 · Clock running

    This is the part the City measures and compares with its target.

  4. 4 · After the permit

    Construction, inspections and occupancy are not part of the processing time.

New home (single family or duplex)

The clock starts after referrals and a complete site servicing review.

Tenant improvement

The clock starts after a complete and accurate building permit application is submitted.

Rezoning

The clock starts after the initial review, once all major deficiencies are resolved.

The times apply to applications that are complete. Missing requirements mean more back and forth and longer times. Source: City of Surrey, Permitting Timelines.

White Rock

No published processing times

White Rock does not publish processing times or targets on its website. Its monthly reports and Building Permits Dashboard count permits issued and their value, not how long they took. Checked November 18, 2026. So there is no fair number to set beside Surrey's. To ask about a specific application, contact the City's Building Division through its building permits page.

What White Rock does publish: how many permits it issues each month, and every development application on its Development Application Information Portal.

Reading these numbers

Three things to keep in mind

  • An average hides the spread. Some applications take much longer than the average, and some much less.
  • A short time for a permit is not a short project. A rezoning comes before the building permit, and construction comes after it.
  • The figures move. They are recalculated over the last 30 days, or six months for rezoning, and the City updates the page from time to time.

Opening a shop or restaurant? See Opening a business: where do I start?