Explore · Explainers
From proposal to completed home
What happens at each stage, who decides, and why an approval is not a home.
A council vote makes the news. It is one step of about eight, and the homes come years later, if at all.
The short version
Approved is not built
Application
City staff
Council: readings and, sometimes, a public hearing
Council
Conditions, then final adoption
Council and the owner
Building permit
City building staff
Construction
The builder
Occupancy
City building staff
Each City's process has its own names and order for some steps, and not every project needs every step. A house on an already-zoned lot may go straight to a building permit.
Step by step
Eight stages, opened one at a time
1. Idea and early advice
Who decides: The owner
An owner or developer talks to City planners before applying. Surrey has a formal pre-application step.
Is it counted? Not counted anywhere.
2. Application
Who decides: City staff
The owner applies to rezone, for a development permit, a variance, a subdivision, or a mix. Staff check it against the Official Community Plan and other policies, and refer it to other departments and agencies.
Is it counted? Listed by each City as "in process".
3. Council: readings and, sometimes, a public hearing
Who decides: Council
A rezoning is a bylaw. Council votes on it at first, second and third reading. If a hearing is required, it is held after first reading and before third. Residential rezonings that fit the plan no longer get a hearing.
Is it counted? Covered in Council Watch.
4. Conditions, then final adoption
Who decides: Council and the owner
Between third reading and adoption, the owner meets the City's conditions: servicing agreements, fees and charges, legal agreements. Then Council adopts the bylaw. This can take months.
Is it counted? Surrey lists rezonings "at third reading" and "final approvals".
5. Development permit
Who decides: Council or staff
In designated areas, a development permit sets the form and character of the building. Variances to the rules need a development variance permit.
Is it counted? Surrey lists development permits in process and issued.
6. Building permit
Who decides: City building staff
Plans are checked against the B.C. Building Code and the City's bylaws. This is when homes start to be counted in monthly permit figures.
Is it counted? Counted monthly by both Cities.
7. Construction
Who decides: The builder
Work on site, with inspections along the way. Timing is largely in the builder's hands, and some permitted projects stall. Surrey's own report to Council says the construction timeline after a permit is "largely outside of the City's control."
Is it counted? Not published by either City.
8. Occupancy
Who decides: City building staff
An occupancy permit says people can move in. Completed homes minus homes demolished are the "net new" homes reported to the Province each year.
Is it counted? Counted yearly, for the Province.
Why it matters
Three reasons approved homes don't appear
- Conditions take time. Third reading is not adoption. The owner may take months to meet the City's conditions, or never do.
- Permits are not construction. A building permit is permission, not an obligation to build.
- Construction is the owner's timeline. Financing, costs and the market decide when shovels go in.
Sources: Local Government Act, sections 464 and 465 (public hearings); City of Surrey, Land Development Application Process; City of White Rock, Development; City of Surrey, Corporate Report R145.